SHANGHAT ELECTRIQUE TRAMWAY — DURATION OF WoRKS

We bind ourselves to begin the works six months after the date in which the agreement. will have been signed, This delay is indeed necessary in order to draw up the execution drafts, order all; supplies for the delivery of materials directly required, From the beginning of the works, we shall be wanting 12 months to hand over to citculae tion the lines 1, 2 and 3, that is to say 18 months from the date of the signing of said agreement, Par Procuration, P. & B. Dunann, B Donaxo.