The scaffolding is now being taken down. The electrical tubing is finished, thus! enabling the last of the plastering to be completed. All the wood floors are laid and the doors and windows are being hang. The building of the boundary wall is begun.

Nieh Chih Kuei Public School for Chinese—This building is practically' finished, except for the heating. he' mud filling is complete and the road is' being constructed, Sikh Gurdwara at Western Police Depét.—The walls are now up to between the first and second floor levels, and the first floor joists have been fixed. The concrete work to st and landings have been commenced.

Sentry Towers at Gaol.—Tie alterations to the tower at the north-east corner of the compound are finished end also the one at the north-west corner, except for the demolition of the centering of the roof and general finishing off.

New Block at Isolation Hospital.—The Contractor has commenced work on this building. The bamboo fence round the is being erected, and materials are being conveyed to the job.

Wuchow Road Market—The concrete work of the roof is completed.

Tungchow Rood Sub-Station.—The concrete of the roof is completed with the exception of the roof over the ventilators.

Dethi Road Sub-Station. crete of the first floor is in the centering of the upper walls is under Markham Road Sub-Station.—The concrete of the first floor is completed and the walls up to the next floor are in course of construction. crete of the first floor is partly in position and the reinforcement of the upper walls is being erected.