Further illustrating: the headway made in the development of hydraulic engineering works in the northwest, the frst period of the construction works of the Wel Hui Canal system Shensi, under the auspices of the Wei Hui Canal Engineering Bureat has been completed and. will be opened for navigation on December 15, The new waterway is 141 kilometres Jong, and the construction work cost "$1,500000, The second period of construction, which will cost around $440,000, will commence Shortly, 'A loan of $1,500,000 was obtained from four leading Chinese banks in Shanghai by the Shensi Provincial Government to finance the project.
Mr. Wu Ching-chao, secretary of the Executive Yuan and Mr. Chia Haieying, deputy director of the Hydraulic "Engineering Bureau of the National Economic Council, have eft for Shensi to attend the inaugural ceremony of the canal.—Central News.