SMC, in hig report for June, says that "the decking of Warren Road Bridge No. 17 hag been surfaced with asphalt. General repairs to Warrett Road Bridge No, 18 have been carried out and general repairs to Fokien Road Bridge and Vu Chung Poo Bridge are in progress, Work was commenced on a length for 431 fect of now reinforced conlerete bunding and two jetties in Hongkew Creek of Fearaa Road, west fof 'Thorne Road. 'The driving of" the reinforced concrete sheet. plies and anchor piles is in progress 'The bunding along the Bund foreshore, from the War Memorial to Jetty' No. 12 and from Jolty No, 15 fo the Bund Gardens, was rotsed by the construction of a reinforced conjerete wall approximately two fect in. height.
At Bund Pontoon No, 15, the stea! stanchions were erected and the At the Pig-Killing Section of the Abattoir, Sawgin. Road, the installa-{tion of the mechantcat plant has been completed and tested. "The wall and floor tiling is on order, and deliveries fare expected during July. 4 At the Public Garden, The Bund, the erection of the new Bandstand Which "has been constructed it limber, has been completed, The structure is now in Use, There were 227 blocks of new Dulldings under construction during,
for approval and 149 plans approved, month, 280 plans' were submitted Valuations of blocks of buildings for assessment purposes made totalled' 134 While 0.828 inspections were: carried
Text read from the printed page and cleaned; old type leaves the occasional error.