Wayside Road and Ward Road have been bricked and sanded.
No. 39 Road, Western District. A number of trees and graves and a josshous" have been removed, a ditch has been made on North side and all private drains from houses in the locality connected to 'A short length of 12" pi been Inid connecting stagnant pond just outside the boundary of the Settlement with North Thibet Riad sewer.
Alabaster Road between North Thibet Road and Kansuh Road has been bricked and sanded.
Winchester Road between North Soochow Road and Alabaster Rosd has been metalled.
Works in Progress on Rout Extensions, No. 39, Westera District, continuing the ditch on North side to Yates Road, constructing on the section between Mohawk and Yates Roads, one 127 culvert, one x 2 culvert and two 3 circular culverts, laying street gullies and connecting same with bricking and sanding.
Yates Itoad. Raising between Seaman's house and No. 39 Road, making ditch and raising with the mud therefrom bs between No, 39 Road and French Concession. and grading, removing graves," buildings and trees, and filling ponds between the Church' and Sinza Revd.
No. 9 Road, Western District, removing lings, goaves and trees, grading road ponds between Bubbling Well Road and Sinza Read.
No. 13 Road, Western District, bricking and swuring Burkill Road, laying concrete pavement in front of the Horse Bazaar property.
No. 37 Road, Eastera District, raising Chusan Road," Wayside Road, Wetmore Road and North Thibet Road, laying kerb and channel.
Outside Rowts.—Rubicon Ronit System. The whole of the culverts are being extend. ed to the full widths of the road.
North Soochow Road between the boundary of the Settlement and the Stone Bridge. The hardwood bunding near the Stone Bridge has been repaired. 220 feet run of 6" pipes have been laid. Chi paving has been laid ne 4 damage by heavy rains. 355 fect run of Places to protect the new ucudann agarist channelling has been laid' where water used to stagnate, and the road throughout the whole length of this section is being bricked and metalled.
Asection of Jessfield Road near Gordon Road has been metalled.
Drainage.—The dearn mouths throughout the Settlement have been cleaned.
AVG" x 1 0 concrete sewer is bei laid in Winchester Road, North Alabaster Road Puvements.—New cement concrete pavements har been laid as follows:—Park Road, both sidles, between Burkill Road and "Sinza Road. Yangtszepoo Road, south sid", near the Hua Sheng Chang Cotton Mill. Siking Road. bob sides, between Kiangse and Honan Roads. Canton Road, north side between Honan Road and Kuangse Road, and south site, between Szechuen Road snd the Bund, The Bund and Kiukiang Roads near the Russo-Chinexe Bank.
Chip pavement has been Laid on the footway, Canton Road, north side, between Kiangse Road and Honan Road. New cement pavements are being laid as follows Chekiang Road, between Nanking and} Ningpo Roads, Kiangse Road, between Hankow and Kiukiang Roads.
Szechuen Road, between Canton and} Sungkiang Roads.
Seward Rowd, between Kungping and/ Muirhead Roads.
Chaofoong Road, between Seward aud} Broadway Roads.
The tar macadam pavoment on Bubbling Well Road between the Horse Bazaar_and Mohawk Road has been repaired to suit the new kerb.
Kerb and Channel—New granite kerb and channel has been laid as tolley Tientsin. oad, between Fukien and Shanse Roads. The Bund and Kiukiang Road, near the Russo-Chinese Bank. Bubbling Well Road, between the Horse Bazaar and M-hawk Road. Carter Road, near Sinza Road, and Sinza Road near Carter Road.
New granite kerb and channel is being laid on Markham Road, north of Sinza Road and Sunghiang "Road, between Kiangse and Honan Roads.
Defective channels have been relaid on Sunzkiang Road between the Buud and Szechuen Roads.
Metulling.—Lengths of roads metalled in each District.
Western District, Central 200 feet run.
Northern, yo"