"After the completion of the channel, three" major "tasks relative to the channel" dredging project will be undertaken, These are the construction of bridges, building of culvers and sluices and afforestation. "Two wooden bridges, each costing about $20,000, will be built presently to span the channel at Wangying ud Lienshut to facilitate communication, while two others may also be built at Tienhu and Chitou. Culverts and sluices are to be constructed to regulate the water for irrigation Purposes as there are large. tracts of wheat elds lying on both siges of the channel, The mud dredged up is now heaped fon both sides of the channel. To event it {rom being swept down Into the channel again by rain and wind, trees and grass will be planted along the banks.
Many Floods
Text read from the printed page and cleaned; old type leaves the occasional error.