Health Dept. Offices and Quarters.—The work done on this building has consisted mainly of pointing the external brickwork and executing the' plaster work, partitions &e,, internally Central Fire. Station Honan Rowl.—'the roof of this building has been completed, ain! the laying of floors and other carpentry work gone on with, The electric light installation is being carried out and good progress has been made with the finishing of the building externally.
Old Cemetery, Pah-sion-jao.—The new brick boundary wall has been built on the east and south sides of the Cemetery, and foundations have been put, in for a further length on the west side. The ditch on the astern portion has been filled Victoria Nursing Institute,—The floor of vie stairewse hall at main entrance huts been laid with encaustic ti